Baseline Quantities Change

Bensouyah MohamedMember for 22 years 9 months
Created
5
1
0
PLEASE HELP¨ME


when i do an updating of my project and find that quantities are changed

how does P3 DISPLAY my new planned values since the DATA DATE

5 replies

Oldest first
  1. 0
    Mk Tse ·
    have you re-schedule the newtwork after data input?
  2. 0
    Bensouyah Mohamed ·
    yes , of course
  3. 0
    Paul Harris ·
    A couple of things to look at:

    1. One option you will need to understand is found under Tools, Options, Autocost Rules. The Freeze Units per time period should be unchecked and then quantities will not change when durations change.

    2. Also you need to check the subtract Actuals from ETC or Actuals Quantities will be added to the At Completion and increase the At Completion value.

    Regards

    Paul E Harris
    www.eh.con.au Eastwood Harris Books
  4. 0
    Bensouyah Mohamed ·
    to Mr PAUL HARRIS

    THANKS A LOT FOR YOUR REPLY

    I HAVE BOUGHT YOUR VERY INTERESTING BOOK ABOUT P3 3.0

    I FIND IT VERY INTERESTING.


    FOR THIS QUESTION . I’ll STUDY YOUR RESPONSE

    AND AFTRER GIVE U THE RESULTS

    THANKS A LOT

    CAN I SEND U BY E-MAIL MY FILE OF PROJECT PLEASE

    THANKS A LOT ANOTHER TIME.
  5. 0
    Bernard Ertl ·
    Paul, I modified your link to work correctly. Please see this post explaining how to add a link correctly.

    Bernard Ertl
    InterPlan Systems Inc. - Project Management Software, Project Planning Software

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?