Relationship&Lag

uid 0
Created
6
1
0
Hello there need help

How can i show the relationship and lags in the column section.

Thanks in advance

Regards

wilfred

6 replies

Oldest first
  1. 0
    Ronald Winter ·
    In reality, you cannot do this in P3. You can show the Predecessors in a column in SureTrak but even there, you cannot show lags.

    It is possible to export this information to a spreadsheet, reformat it, and then import it back as an Activity Code. You could display that activity code as a column. This method will not automatically update itself if you should make any logic changes without repeating the above-described process again. Good luck!
  2. 0
    Forum Guest ·
    Thanks It helps Regards wilfred
  3. 0
    Mk Tse ·
    Wilfred, may I know why need this presentation, it seems a presentation by Project.

    From an export spreadsheet and reformat it as code is not an easy job.
  4. 0
    Anonymous ·
    I did not reformat and import it back I just need some reports to show my manager so he can make a comment easily
    and spreadsheet is ok.

    Thanks again,

    wilfred
  5. 0
    Mk Tse ·
    Have you try the tabular report on relationship? The default one is accept. If you want more pretty, tailer make one to fit your purpose.
  6. 0
    Anonymous ·
    Yes, Its good enough

    Thanks,

    wilfred