Display Code description

Forum GuestMember for 17 years 8 months
Created
2
3
0
Hi guys,

Can somebody help me to show activity code descriptions or WBS code descriptions on the activity bar?

Thanks

2 replies

Oldest first
  1. 0
    Mk Tse ·
    As alternative, export the description and put them as a log of the activity. Then display the log against bar.
  2. 0
    Paul Harris ·
    When I am required to show the Activity Code description in columns or on bars I open the project with SureTrak and there is an option in the Options, View form to show Activity Codes descriptions and not the Code Values.

    There are many other good features in SureTrak and I advise anyone who has P3 that SureTrak is a great companion tool. It has additional features such as:
    - Showing Constraints, Constraint Dates, Log 1-10 and Log Record in Columns
    - Organize has a number of options such as organizing by Activity ID and Resource Units not available in P3
    - Copy and Paste from a spreadsheet.

    Paul E Harris
    Eastwood Harris Pty Ltd
    Planning and Scheduling Book Publishers
    www.eh.com.au