Activity Codes vs WBS
In the Open Standard
Patrick ZwinkelsMember for 24 years 6 months
- Created
- 14
- 1
0
I am looking for a white paper, which explains when to use activity codes rather than the wbs in Primavera.
I spoke to a collegue about the fact that often one wbs is created in P3 which actually comprises of multiple structures and therefore becomes a beast of a thing...
When executing a project, I often use multiple activity codes to present the schedule, depending on the situation, instead of using the wbs function.
In my view, a project can be broken down into a number of ways (structures), such as by geographical area, by system, by phase, by company, by workpackage etc.
So, I’m looking for some published pieces to confirm my views...
I spoke to a collegue about the fact that often one wbs is created in P3 which actually comprises of multiple structures and therefore becomes a beast of a thing...
When executing a project, I often use multiple activity codes to present the schedule, depending on the situation, instead of using the wbs function.
In my view, a project can be broken down into a number of ways (structures), such as by geographical area, by system, by phase, by company, by workpackage etc.
So, I’m looking for some published pieces to confirm my views...
14 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?