hammok activity update

Forum GuestMember for 17 years 8 months
Created
5
5
0
when i whant update hammok activity in p3 , "cost this period" are negative .
I whant some information about update hammok activity

5 replies

Oldest first
  1. 0
    Mk Tse ·
    Which field you are updating in Hammock?
  2. 0
    Luca Basile ·
    Hammock should be update automatically by P3.
    As per instruction given in the manual for summarizing activities.
    You should not need to update them, as well as the wbs activities.
  3. 0
    Rahil Khan ·
    since hammocks are attached to the earliest start date and the latest finsh dates, any updates will automatically will be incorporated
  4. 0
    Luca Basile ·
    Why You do not use Wbs activities?
    The hammock is just considering the first with the s-s relat. and the end with f-f relationship, in a chain.
    If any activity in the middle of the chian is going out of the originally first and last teh hammock is not covering it any more. Or You have to chekc every update time.
    With Wbs just put it and define the level must summarize.
    Much more easier. If your purpose is just summarize a group of activities.
  5. 0
    Eric Chou ·
    Attached is the write-up by myself regarding Hammock Activities. Please review for your reference.

    Go to the
    http://www.htcprojectcontrols.com/TTB2004-6.pdf

    Eric Chou, PE
    HTC Project Controls, Inc.