Oldest first- 0HJHenry John Bormate ·Hi Harzelli!
I have the same query with Carlos, I tried the step you mentioned ( File => Open => "tick" exclusive & open the file i want to edit the activity ID) but still the ID is in uneditable mode, can you help me please.
Another thing is, I want to change the title of my WBS, is their also a way to do that?
Thnx & more power... - 0RDRafael Davila ·You can Change Activity ID within a project without Exclusive Access, this is another option.
Please follow the link.
http://www.htcprojectcontrols.com/TTB2003-1.pdf
Perhaps Carlos had a wrong value for ExclForActIDEdit line, default should be 1.
To change WBS titles go to Data>WBS and change titles at will.
Best Regards,
Rafael
- 0RDRafael Davila ·Osama,
One option might be:
First backup your job, then try selecting all activities and follow with a Copy and Paste, the software will ask you for the rules to change ID’s. Then delete "old" activities.
Make sure all data copied correctly; don’t know what will happen with period actual and other data.
If you copy and paste separate groups you might lose the links between activities spanning separate groups so it is important you copy all at once unless willing to manually check on missing links.
In Spider Project I can change my activities ID’s by importing a CSV file that can be generated from almost any text editor, word processor, spreadsheet and database application, maybe someone else can provide you with a clue on how to do this in P3.
Good luck,
Rafael - 0AKAkhtar Khan ·Hi,
To change Act Id thru Global Change u should use Global change function Left(Act,XX) or Right(Act,XX) where XX is the no.of digits u want to retain.e.g ACT ID is 1234567890
use Global Change Formaula
ACT EQ ABC & Right(ACT,7)
The result will be ABC4567890.
Using this type of Global Change u can change ur Act Id is just few mins.
- 0OWOsama Warid ·Greetings
Thanks for all replies
Rafael
This is the best to do it quickly but for sure there will be some information will be lost
Akhtar
This will change part of the ID, if you can to change completely it will be perfect,
The problem that I face is how to make the new ID take the sequence
Jvito
If we have 4000 activity * 5 sec to change each item this will take around 1 working day. This if I follow the mentioned method
Regards,