Alfon Lyndon JosonMember for 22 years 6 months
Created
5
4
0
Dear Experts

Is there a command in Global Change where i can delete the Actual Starts, Actual Finish and so with the Relationships like FF, FS and the likes?

Thanks in advance...

ALFON
SCDC

5 replies

Oldest first
  1. 0
    Alfon Lyndon Joson ·
    Hi Dragos..

    Can you further explain what to do in Activity.xls in deleting relationships?

    Thanks and best regards..

    ALFON
    SCDC
  2. 0
    Luca Basile ·
    You can also export in dbf format activity id, description, the dates and percentage and remaining duration.
    Make the changes and import back.
    When You import the early and latest dates You have also a fields "ESA" and "EFA" that is actually reminding that the dates areactual. In this just take out the "A".
    May be You can have a better felling of what You are doing than using a global change.

    When You import remember, if You use excel, define the database range (Insert->Name), then save as DBIII format, or P3 will not read it.
    When import in P3 close the file in excel or access!


    If during the progress You changed the logic, you have to re-establish the original logic, otherwise no problem.
  3. 0
    Forum Guest ·
    I recently wanted to delete all of the relationships in my schedule. P3 help directed me to open my p3.ini file and add a line to the Options. If you run Windows, find the p3.ini file in the WIN/or/WINNT folder under your C:. Open the P3.ini folder and find the Options category. At the bottom add the line "Unlinkallrels=1". Save the file then and open your project. Highlight the specific activities you want to unlink and select the unlink button. All of the links between the highlighted activities you had will be deleted. Search under "P3.ini" in P3 Help. Good luck.
  4. 0
    Mk Tse ·
    Alternative, make a copy of the project. Then delete all activities in the copy.
    Export all information EXCEPT relationship from source and import to the copied project.
    Hope help.
  5. 0
    Adnan Kocak ·
    Hi Alfon,

    Yes the way it’s going from Glabel Change. But be Carefull, before you run it, please run in trial run and check the activities.

    Adnan