Dear Sir/Madam,
I am a fulltime diploma student currently trying to complete an assignment on project managemnt subject.
I had been using P3 since the beginning of this new semester i.e. 9 days ago.
Whilst the input to the website are massive from various parts of the world, I am still couldn’t find the solution to my problem regarding scheduling matters in P3.1.
The problem:
I have this dummy project about 10 activities with each Ori.Duration.
In order to execute each activity I build up Resources: Labour(no), Equipment(no) and Material.
I had also assigned cost to each resources above, by daily wages.
Some of the activity are Lump Sum so I have to assigned only cost ONLY in respective activity .
Well, those are the cost that the contractor will or need to spend in order to complete the physical activities till completion contract date.
Now, the contractor also has an Income to the project. The income will be base on the claim made through BQ(bill of quantities) on the % of work completed. From the BQ, I
Breakdown the cost to fit the each activity in P3 schedule i.e. assigned each cost to each activity.
My plan is that during the tracking of the cost project, I wish I could have these information below:
Act ID
Act Description
OriDur
ES EF
LS LF
TotFloat
ResourceCost (Spend)
(a)Target
(b)Actual
Claimed fr BQ (Income)
(c )Target
(d)Actual
Variances:
1. Res.Variance (b) & (a)in % and $.
2. Claimed Variance (c) & (d) in % and $
3. Actual Variance (cost spend) vs (actual claimed fr BQ).
Key
( a) The total cost of all resources needed in each activity or
to each activity in Lump Sum.
(b) Actual cost of (a) used.
Calculation, (b) = % completion in each activity x (a).
( c) Cost breakdown to each activity extract from BQ.
(d) Actual cost of ( c) claimed
Calculation, (b) = % completion in each activity x ( c).
The challenge:
I tried to get the above info (cost) in P3 using Activity Detail Form , Resource, Budgets, Cost; but it drives me crazy. The cost ( Target claimed from BQ (c ) ) did not come out in columns.
In P3, there are various definitions like Budgeted Cost, BCWS, BCWP, ACWP, Planned Value etc. The only cost input during the scheduling task are in Resource, then from Activity Detail Form (as described). When I list down all the above in columns , the only cost appeared in the layout Gantt is Budgeted Cost i.e. taken from resource cost. How am I going to assigned ( c) ?
I thought (a) = BCWS, but in column BCWS there nothing except Budgeted Cost.
Could you please help me on how am I going to incorporate the above info in P3.
Normally in forum its only stated on philosophical aspect and NOT the core of scheduling task i.e. the actual step on how to get what we actually need.
Your help and cooperation are all highly appreciated.
Yours Sincerely,
Taram Hantam
Full Time Student
Diploma Building, UiTM
Shah Alam
Malaysia
e-mail: hippietrail111@yahoo.co.uk
I am a fulltime diploma student currently trying to complete an assignment on project managemnt subject.
I had been using P3 since the beginning of this new semester i.e. 9 days ago.
Whilst the input to the website are massive from various parts of the world, I am still couldn’t find the solution to my problem regarding scheduling matters in P3.1.
The problem:
I have this dummy project about 10 activities with each Ori.Duration.
In order to execute each activity I build up Resources: Labour(no), Equipment(no) and Material.
I had also assigned cost to each resources above, by daily wages.
Some of the activity are Lump Sum so I have to assigned only cost ONLY in respective activity .
Well, those are the cost that the contractor will or need to spend in order to complete the physical activities till completion contract date.
Now, the contractor also has an Income to the project. The income will be base on the claim made through BQ(bill of quantities) on the % of work completed. From the BQ, I
Breakdown the cost to fit the each activity in P3 schedule i.e. assigned each cost to each activity.
My plan is that during the tracking of the cost project, I wish I could have these information below:
Act ID
Act Description
OriDur
ES EF
LS LF
TotFloat
ResourceCost (Spend)
(a)Target
(b)Actual
Claimed fr BQ (Income)
(c )Target
(d)Actual
Variances:
1. Res.Variance (b) & (a)in % and $.
2. Claimed Variance (c) & (d) in % and $
3. Actual Variance (cost spend) vs (actual claimed fr BQ).
Key
( a) The total cost of all resources needed in each activity or
to each activity in Lump Sum.
(b) Actual cost of (a) used.
Calculation, (b) = % completion in each activity x (a).
( c) Cost breakdown to each activity extract from BQ.
(d) Actual cost of ( c) claimed
Calculation, (b) = % completion in each activity x ( c).
The challenge:
I tried to get the above info (cost) in P3 using Activity Detail Form , Resource, Budgets, Cost; but it drives me crazy. The cost ( Target claimed from BQ (c ) ) did not come out in columns.
In P3, there are various definitions like Budgeted Cost, BCWS, BCWP, ACWP, Planned Value etc. The only cost input during the scheduling task are in Resource, then from Activity Detail Form (as described). When I list down all the above in columns , the only cost appeared in the layout Gantt is Budgeted Cost i.e. taken from resource cost. How am I going to assigned ( c) ?
I thought (a) = BCWS, but in column BCWS there nothing except Budgeted Cost.
Could you please help me on how am I going to incorporate the above info in P3.
Normally in forum its only stated on philosophical aspect and NOT the core of scheduling task i.e. the actual step on how to get what we actually need.
Your help and cooperation are all highly appreciated.
Yours Sincerely,
Taram Hantam
Full Time Student
Diploma Building, UiTM
Shah Alam
Malaysia
e-mail: hippietrail111@yahoo.co.uk
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?