Forecast to go
In the Open Standard
David WattersMember for 23 years 9 months
- Created
- 13
- 1
0
Hi
Have a problem, and would like to know if anyone has some possible solutions.
I am using P3 version 3.1 and would like to know how to set a forecast completion quantity for an activity that has currently 0% progress WITHOUT it affecting the current budget. In practical terms, I want to see the variance between planned and actual on an activity.
I suspect it a function hidden within the Autocost rules, but would like to know if anyone has completed this via another method.
Many thanks in return for you help in advance :¬)
Have a problem, and would like to know if anyone has some possible solutions.
I am using P3 version 3.1 and would like to know how to set a forecast completion quantity for an activity that has currently 0% progress WITHOUT it affecting the current budget. In practical terms, I want to see the variance between planned and actual on an activity.
I suspect it a function hidden within the Autocost rules, but would like to know if anyone has completed this via another method.
Many thanks in return for you help in advance :¬)
13 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?