Skip to content

Forecast

Joe goodmanMember for 21 years 6 months
Created
0
1
0
Dear all,

In plotting the s-cuves for the EVM, I usually use the planned, Earned and Actual, my project requires plotting the forecast, what I do is getting the cummulative CPI at the current date and divide all the budgeted quantities for the following date by CPI and plot these values as Actual.Is that right,and how to find the new completion date,can I do all that with P3,How? and then trasfer it to excel. Please advise.

Joe

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?