Resource Loading

Adham ShabbaraMember for 22 years 3 months
Created
3
1
0
Hi everyone,

can anyone please advise what resource curve is better to use while loading and assigning manpower resource for a specific activity?? linera or bell shape curve??

Pls. asist

thanks,

Adham

3 replies

Oldest first
  1. 0
    Luca Basile ·
    It depend from the nature of the activity.
  2. 0
    David Watters ·
    Linear - We had a HUGE ammount of debate on this recently when we rebaselined our Plan. We opted to profile certain activites for PDMS modelling, and no-one could agree which one to use. When they did settle on a curve, they didn’t think it fitted their exact requirements, SO bring out the hatchet and build in more detail on linear spreads.

    Cool idea for Primavera to build it in, but when the PMs and Proj Engineers get into it, it never seems quite good enough.

    Saying that, Back load for engineering deliverables, and bell load for activities that include multiple revisions, to allow for reduces effort in change as document progresses.
  3. 0
    Mk Tse ·

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?