Planned % Complete S Curves at EST & LST
In the Open Standard
Mike SwanMember for 22 years 4 months
- Created
- 5
- 1
0
I’m interested in producing planned % complete S curves at EST and LST. Then track actual % complete as the contract progresses.
Does anyone know how to calculate these planned percentages from the target programme?
My solution so far is to take a copy of my target programme and update progress using the auto functionality for each projected update date. This gives me EST.
Then take another copy and use global change to move all the EST to LST and repeat the process. A time consuming exercise.
Does anyone know how to calculate these planned percentages from the target programme?
My solution so far is to take a copy of my target programme and update progress using the auto functionality for each projected update date. This gives me EST.
Then take another copy and use global change to move all the EST to LST and repeat the process. A time consuming exercise.
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?