Resource Requirement in P3
In the Open Standard
Subhash Babu ChandrabhatlaMember for 22 years 3 months
- Created
- 1
- 1
0
I am basically planning for Road Project. In the project we have Excavation in Hard Rock, Soft Rock and etc. In P3 I have defined the Resource for the project and assigned them to each activity.
Considering a particular cse where after assigning ONE EXCAVATOR simultaneously to two activities (Exc. for Hard Rock & Exc. for Soft Rock) I got some finish dates. Now my querries are
Q1. If I want to reduce the duration of the completion of above activities How should I?
Q2. If I were to increase the resource how should I go for and bring about the optimal use of it?
May pleas suggest?
Considering a particular cse where after assigning ONE EXCAVATOR simultaneously to two activities (Exc. for Hard Rock & Exc. for Soft Rock) I got some finish dates. Now my querries are
Q1. If I want to reduce the duration of the completion of above activities How should I?
Q2. If I were to increase the resource how should I go for and bring about the optimal use of it?
May pleas suggest?
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?