Long Activity IDs

Ismail VandeliwalaMember for 22 years 5 months
Created
5
1
0
Currently we are using acitivity id’s that are 10 characters long. Are u having problems with activity id’s more than 6 characters or u do not want to use an activity id with more than 6 characters?

5 replies

Oldest first
  1. 0
    Shahzad Munawar ·
    Why did you kept ID more than 10 characrters? Its your project/ Phase requirement?

  2. 0
    Ismail Vandeliwala ·
    Yep in our project it is a contractual requirement to have the activity id’s clearly identifying the elements of the work hence it has to be 10 characters the maximum that P3 allows
  3. 0
    Marc Borburgh ·
    The length of the activity ID is very much related to teh type of project. I’m doing a lot fo work (if not all my work)in the petro-chemical enviroment and 9 out of 10 times the planning is based on the Enterprise / Workorder system used by our clients.

    When transfering data from the Workorder system to the planning, we need to make sure that during this transfer existing tasks can be updated. A combination of the Workorder number and the task id will determine the length of the activity ID, which is 99.9% of the times 10 characters.

    As I said, its purely depending on the type of plan and the enviroment.
  4. 0
    Steven Oliver ·
    Just a suggestion, but the Activity ID is really just the unique identifier P3 uses to tie in logic, resources etc. If you require longer ID’s for an activity, try Custom Data Items.

    HTH
  5. 0
    Mk Tse ·
    Ismail, for your question, there is no problem on P3 if the ACT ID is 10 characters or any less than 10.

Log in or join to reply