Finish Flag Query

Samantha McCullochMember for 23 years 1 month
Created
3
2
0
I am trying to anaylise a P3 schedule given to me which has a Finish Flag. I have made a Target schedule of the original schedule, and am currently trialing some different duration options on the Target 1 I have made. Whilst changing some durations I have noticed that the Finish Flag (which happens to be the Project Complete Activity) moves out......which I would expect if it had Predeccessors or successors....which I cannot see. Plus I have looked for a constraint...non to be seen.

Can somebody tell me how this would happen, as I have never used the Type: Flag activity before.

Thank you
Samantha

3 replies

Oldest first
  1. 0
    Steven Oliver ·
    Essentially, if a finish flag activity has no predecessors, then it will default to the latest early finish of the rest of the plan.

    Incidentally, a finish flag cannot have a successor (in the same way as a start flag cant have a predecessor.

    HTH
  2. 0
    Samantha McCulloch ·
    Brilliant. Thank you for your quick reply.

    This absolutely makes sense.

    Good planning.

    Samantha
  3. 0
    Steven Oliver ·
    Ooops. Having just reread my earlier post, Can I point out that a start flag can have a predecessor, but not a successor.