Suspend/Resume/Expected Finish Question
In the Open Standard
Marc BorburghMember for 22 years 5 months
- Created
- 9
- 3
0
Hi all,
I have a High Level Planning and for each task (phase) a gate has to be passed. From the Project Manager I get the Actual start and a date that he will issue his documents for that phase. After issueing the documents, shareholders will have to approve so we can move to the next phase.
I have a phase that started in Nov04, the documents will be issued May 2nd of 2005 and approval is expected Jun 24th 2005.
So I have:
an AS on Nov04
a Suspend date on May 2nd
a Resume date on Jun 24th
an Excpected finish on Jun 30th
a data date on April 1st.
Now I expected to see that the bar would show a working period from the Data date till the Suspend date and a working period from the Resume Date till the XF date.
It is however showing a non-working period from the Data Date till the Resume Date.
Why don’t I have a working period from the Data Date to the Suspend Date?
I have a High Level Planning and for each task (phase) a gate has to be passed. From the Project Manager I get the Actual start and a date that he will issue his documents for that phase. After issueing the documents, shareholders will have to approve so we can move to the next phase.
I have a phase that started in Nov04, the documents will be issued May 2nd of 2005 and approval is expected Jun 24th 2005.
So I have:
an AS on Nov04
a Suspend date on May 2nd
a Resume date on Jun 24th
an Excpected finish on Jun 30th
a data date on April 1st.
Now I expected to see that the bar would show a working period from the Data date till the Suspend date and a working period from the Resume Date till the XF date.
It is however showing a non-working period from the Data Date till the Resume Date.
Why don’t I have a working period from the Data Date to the Suspend Date?
9 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?