Skip to content

BACK-UP AND RESTORE SCHEDULE

Kris HarryMember for 22 years
Created
2
2
0
Hi,

At times when we back-up schedule on a floppy and then restore on another PC we get a message "target project not found". What does this indicate. Do we have to create a target project.

2 replies

Oldest first
  1. 0
    Maria Ahlberg ·
    No, you do not have to crate a target project.
    Most likely you had a target project together with the project you backed up. When you do the back up, I guess you only did a back up for the main project, and not for the target project. If you dont need the back up for the target project (and dont want to do a back up for it) then you can chose project overview/targets and delete the targetproject that P3 is looking for when you open the backed up project. Then you can open your plan.
    yours/
  2. 0
    Kris Harry ·
    Thanks Maria, I will try this

    Kris

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?