Relationship between RD & TF
In the Open Standard
Kashyap MothaliMember for 21 years 6 months
- Created
- 6
- 2
0
I always thought that the Remaining Duration "RD" and the Total Float "TF" values are inversely proportional i.e., when the RD becomes less, the Total Float either remains the same or improves.
However, I have a Contractor’s schedule, which reflects just the opposite on a particular activity! When I increase the RD and the OD on this activity (due to extra work), the Total Float value also seems to improve. I don’t remember having seen this occur before. Could anyone please explain why this is happenning?
Not to mention that there are numerous lags along with all four types of relationships in this schedule (SS, SF, FS & FF).
Regards,
Kashyap Mothali
However, I have a Contractor’s schedule, which reflects just the opposite on a particular activity! When I increase the RD and the OD on this activity (due to extra work), the Total Float value also seems to improve. I don’t remember having seen this occur before. Could anyone please explain why this is happenning?
Not to mention that there are numerous lags along with all four types of relationships in this schedule (SS, SF, FS & FF).
Regards,
Kashyap Mothali
6 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?