P3 Activity Types

Brendan DonovanMember for 22 years 11 months
Created
3
2
0
Is there a way to set the activity types (eg milestones hammocks etc) as a column on the bar chart in p3, so you can filter and more importantly fill the cell rather than doing it one by one.

3 replies

Oldest first
  1. 0
    Jaco Stadler ·
    Format - Column - + (Add) Activity Type.

    You do not need a Column for a Filter but this allow you to type in the activity type. You can also export and import this from xls.

    Cheers
  2. 0
    Paul Harris ·
    Grab a copy of SureTrak, you can open and set activity types with SureTrak, + a whole load other things that P3 can not do.

    Paul E Harris
    Eastwood Harris Pty Ltd, Melbourne, Australia
    Planning and Scheduling Book Publishers, Training & Consulting
    www.eh.com.au
  3. 0
    Bijaya Bajracharya ·
    Brendan,

    Nice to see you. How are things with you?

    Adding a column for activity type is possible and done the same way as for any other variables. However you cannot fill cell in that column. If you want to do anything of that sort, you can use global change.

    Bijaya