Construction Project Control
In the Open Standard
Mirza Imam BaigMember for 23 years 5 months
- Created
- 3
- 3
0
Hi Planners,
I have been working as a Planning Engineer for an Engineering Company, involved in the Design of Industrial and Infrastructure Projects.
In our Project Control, I have only Man-hours as Budget. We divide the total project man-hours/ per discipline and then per drawings and track the Progress, variance against the Man-hours consumed.
My question is, how the project is controlled when it comes to a Construction Project. Lets say I have 4 items in my Bill of Quantities. Say
1 Excavation to receive footings....201 Cu.m.
2 R/Concrete for the footings...65 Cu.m.
3 R/Concrete for the Columns... 38 Cu.m.
4 R/Concrete for the Slab ...24 Cu.m.
As I understand, for a Level 4 Schedule the items in the Bill of Quantity will act as the Tasks. And when it comes to resources, what shall be the resources? Say for Item No. 2 (Reinforced Concrete for the footings), whether it will be the quanity of Reinforced Concrete, or Manpower to accomplish the task or Equipment or all the three. Okay, if it’s Concrete, we can input the quantity and its unit price. But when it comes to Manpower and Equipment, how can we quantify the manpower required for each tasks. Is there any reference for different items? And how it will be updated?
As I am working with the Design Consultant, I did not come across the Construction Project Control. But I am very much eager to know how the projects will be Controlled in Construction. Hope someone will help me on this. Thanks in advance
I have been working as a Planning Engineer for an Engineering Company, involved in the Design of Industrial and Infrastructure Projects.
In our Project Control, I have only Man-hours as Budget. We divide the total project man-hours/ per discipline and then per drawings and track the Progress, variance against the Man-hours consumed.
My question is, how the project is controlled when it comes to a Construction Project. Lets say I have 4 items in my Bill of Quantities. Say
1 Excavation to receive footings....201 Cu.m.
2 R/Concrete for the footings...65 Cu.m.
3 R/Concrete for the Columns... 38 Cu.m.
4 R/Concrete for the Slab ...24 Cu.m.
As I understand, for a Level 4 Schedule the items in the Bill of Quantity will act as the Tasks. And when it comes to resources, what shall be the resources? Say for Item No. 2 (Reinforced Concrete for the footings), whether it will be the quanity of Reinforced Concrete, or Manpower to accomplish the task or Equipment or all the three. Okay, if it’s Concrete, we can input the quantity and its unit price. But when it comes to Manpower and Equipment, how can we quantify the manpower required for each tasks. Is there any reference for different items? And how it will be updated?
As I am working with the Design Consultant, I did not come across the Construction Project Control. But I am very much eager to know how the projects will be Controlled in Construction. Hope someone will help me on this. Thanks in advance
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?