Week Starts

Zhao HuangMember for 22 years 10 months
Created
1
1
0
Hi Planner,

Weekly report cut off date should be change from monday to thursday. Plan had been developed, how to change the week starts day?

Thank you!

Jonathan

1 reply

Oldest first
  1. 0
    Andrew Podolny ·
    Data-->Calendars-->Global Calendar-->Standard-->Week starts on

Log in or join to reply