Pipeline Project

Ajit mMember for 22 years 2 months
Created
1
1
0
Hello friends...

Can anyone provide me the activity details of a pipe line project as urgent.

I’ll be oblized to get any feed back regarding construction plan for a pipe line project.

Any additional guidelines or job knowledge also will highly help me.

Thanks
Aj

1 reply

Oldest first
  1. 0
    Philip Jonker ·
    It is simple,

    Coceptual design

    Engineering,

    Construction:

    Site Clearance
    Excavation
    Bedding
    Pipe laying
    Fit-up and tack
    Welding
    QA Clear Welding
    Pipe wrapping
    Spark testing
    QA Clear Spark Testing
    Galvanic Protection
    QA Clear Galv Prot
    Backfill and compaction
    QA Clear BACKFILL

    and so forth,

    good luck

    Regards