Suspend & Resume

Shareef Abdul AzeezMember for 21 years
Created
2
3
0
Hello,

I would like to know how Suspend & resume function is used..

Usually during updation of progress on activities, on activities which are suspended after they had some progress, I used to keep them as it is, ie their percentage complete was kept the same till the activity finally resumes finishes.

* What are the results on not using suspend & resume function?

* Is it possible to just suspend an activity and proceed with scheduling as I would not know at the instant when the activity would resume?

Please provide your views....

2 replies

Oldest first
  1. 0
    Harzelli Bouasria ·
    Hi
    you have the choice:
    1. if you don’t know resume date, let it open
    2. else you nmust put the suspend and resume date
    good luck
  2. 0
    Shareef Abdul Azeez ·
    Hi

    thanx for your reply.

    I would lke to know what would happen if I donot use suspend and resume for an activity which has actually been suspended coz of some obstructions.

    I think it will affect the costing part in P3. or may be the remaining duration.

    Am I right?