Suspending an activity

Efren LabayMember for 19 years 9 months
Created
2
4
0
Hi P3 Masters,

Here is my question, i have a detailed schedule and one activity say activity ’A’ has a orig duration of 20 days. It starts and after 5 days with 20 percent completion some problems happened were the consultant ask to suspend this activity. After 10 days problems was solve thus activity resumes but again after 7 days with 60 percent completion another problem happened and it must be suspended again but P3 allows one time suspension only, it is loaded with wt. % and resources, so what is the best way to do in P3 scheduling without affecting BCWS and BCWP.


Thanks...

2 replies

Oldest first
  1. 0
    Steven Oliver ·
    Personally, if you are instructed to suspend an activity, IMHO I would introduce a new activity to cover the period of suspension.

    The suspend feature in P3 is not at all visible, and if you ever need to retrace events to justify (for example) an EOT claim, it would be very easy to miss.
  2. 0
    Efren Labay ·
    Thanks Mr. Steven simple and very smart technique