Remaining duration
In the Open Standard
Harzelli BouasriaMember for 18 years
- Created
- 4
- 1
0
Hi folks
how can you have remaining duration without having to give % complete, (task don’t have a resources)
example:
civil works: on data date: 10NOV09
early start: 10NOV09
early finish: 20NOV09
OD=10days RD=10days
civil works: on data date: 15NOV09
Actual start: 12NOV09
early finish: 24NOV09
OD=10days RD=10days
how can you explain this ????
how can you have remaining duration without having to give % complete, (task don’t have a resources)
example:
civil works: on data date: 10NOV09
early start: 10NOV09
early finish: 20NOV09
OD=10days RD=10days
civil works: on data date: 15NOV09
Actual start: 12NOV09
early finish: 24NOV09
OD=10days RD=10days
how can you explain this ????
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?