how can I change the Early finish project date
In the Open Standard
Filippo CARTAMember for 21 years 5 months
- Created
- 6
- 2
0
Hello Folks,
I have a project starting on the 2nd of may and finishing in march 2006
When I created it, P3 set up 2 nov 2005 as a early finish date for the project. Now all the my activities or chain of activities that passed this date show up as critical.
I have tried to set up "the project must finish on march 2006" but still the eraly finish date for the project remain 2 nov 2005 and the total float is calculated on this date.
is there any way to change it? I’ve just made a couple of test and found out that in my case P3 calculate the early finish date for the project adding 6 months to the data date(data date 02/05/2005 early finish date 02/11/2005).
If I schedule the project to a data date let say 20/05/2005, the finish eraly date becomes 20/11/2005
Any help?
Cheers
Luca
I have a project starting on the 2nd of may and finishing in march 2006
When I created it, P3 set up 2 nov 2005 as a early finish date for the project. Now all the my activities or chain of activities that passed this date show up as critical.
I have tried to set up "the project must finish on march 2006" but still the eraly finish date for the project remain 2 nov 2005 and the total float is calculated on this date.
is there any way to change it? I’ve just made a couple of test and found out that in my case P3 calculate the early finish date for the project adding 6 months to the data date(data date 02/05/2005 early finish date 02/11/2005).
If I schedule the project to a data date let say 20/05/2005, the finish eraly date becomes 20/11/2005
Any help?
Cheers
Luca
6 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?