Transfer from P3 to Microsoft Project 2002

Jihad DanielMember for 21 years 5 months
Created
1
1
0
Can you give me the best way to transfer a P3 schedule to Microsoft Project 2002 without losing relationship links or other datas?

1 reply

Oldest first
  1. 0
    Frank Borcherdt ·
    J,

    Use the MPX Conversion program installed with P3 in the Primavera Program Group. It allows you to write an write an MPX files from a P3 Project Group. Use the help button within this program to check how the P3 data maps to MSP.

    Project 2002 can open MPX files.

    HTH