Set activity type hammock for a set of tasks.
In the Open Standard
Gün GöksuMember for 21 years 6 months
- Created
- 5
- 1
0
Hello everyone,
Thank you to all who take the time to respond to all those questions. till now I have found all the answers to my questions as they have been asked and answered before.
This one I couldnt find.
I need to convert a certain number of tasks to hammocks.
(set Activity Type = hammock)
But I cant find a way to get the SYST column to show in the export files.
and a global change I could not make it to work.
a little detail.
Activity ID’s that need to change are all L????.?S
IF ACT EQ L????.?S
THEN SYST EQ "Hammock"
does not work. (I have tried hammock, "hammock", h, and whatever has come to my mind).
any other way to do this fast??
Thank you. :)
Gün.
Thank you to all who take the time to respond to all those questions. till now I have found all the answers to my questions as they have been asked and answered before.
This one I couldnt find.
I need to convert a certain number of tasks to hammocks.
(set Activity Type = hammock)
But I cant find a way to get the SYST column to show in the export files.
and a global change I could not make it to work.
a little detail.
Activity ID’s that need to change are all L????.?S
IF ACT EQ L????.?S
THEN SYST EQ "Hammock"
does not work. (I have tried hammock, "hammock", h, and whatever has come to my mind).
any other way to do this fast??
Thank you. :)
Gün.
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?