export from P3 into xls including grouping structu

Eckart SchenckMember for 21 years 4 months
Created
6
1
0
Hi,

is there a way to export a P3 schedule to excel without losing the grouping structure?

Thanks!

Heinz

6 replies

Oldest first
  1. 0
    Jaco Stadler ·
    Henk Export the Activity Codes as Well then when you are in XLS you just sort or Subtotal By Structure
  2. 0
    Razi Khan ·
    Hi,

    Export with "Activity Code" Columns also and then sort and group in Excel as per requirement.

    Cheers.
  3. 0
    Eckart Schenck ·
    I’m familiar with sorting by act codes in xls.

    The problem comes when you communicate with somebody who doesn’t know well the act code structure and doesn’t have P3 either. In such case it would be good to have an excel export with the grouping...

    Heinz
  4. 0
    Razi Khan ·
    Then why don’t you give report in pdf format instead of Excel.
  5. 0
    Mk Tse ·
    Is web publish is an alternative?
  6. 0
    Zhang Haixiang ·
    What you need to do is just sort your activities then add a group title.

    if you have too many to add, try excel’s outline worksheet function.( I’m using excel 2002,it has the ability to group rows/columns)