P5 Save Grouping/Sort/Layout/Page Setup Per Project

Abeer MahmoudMember for 18 years 3 months
Created
3
1
0
Hi All

In P3:
When I open project #1; it opened with original grouping/sort and layout/page setup with out any modification which I closed on pervious day.

And when I open a project#2 on the same time it opened with original grouping/sort and layout/page setup with out any modification.


In P5:
I open project #1 with it is original grouping/sort and layout/page setup.

And when I open a project#2 on the same time it opened with project #1 grouping/sort and layout/page setup.

So every time I must establish from scratch project #2 grouping/sort and layout/page setup included header and footer.

And accordingly when I opened after that project #1 it opened with project #2 grouping/sort and layout/page setup included header and footer.

How can I solve this problem? I Need To Save Grouping/Sort/Layout/Page Setup Per Project Not Per Projects.

Please I need your advice.
Regards,
Abeer Mohamed

3 replies

Oldest first
  1. 0
    Arnold Puy ·
    Hi Abeer,

    I don’t really get what you mean but in my understanding, you need to save the layout everytime you edit & alter each layout, rename and open evrytime you need it.

    Regards.

  2. 0
    Abeer Mahmoud ·
    Hi Arnold,
    It worked.Thanks for your fast replay,
    I appreciate your usual support very much

    Abeer
  3. 0
    Abeer Mahmoud ·
    James kindly note that I tried your steps before and it didn’t work.
    But when I went to admin first as Tom said it worked.
    Thanks for both of you for fast replay.

    Abeer