logic in premavera p3 (Urgent please )
In the Open Standard
Mohammed FoudehMember for 21 years 6 months
- Created
- 11
- 3
0
hello all:
i have (2) questions regarding the logic and sequencing in p3:
i will give an example to explain question (#1):
* the activity "block work" for ground floor starts after Steel Erection (its a steel structure building) and continue after the finish of mezzanine slab to complete the balance block there,my question is: what is the best method to link these activity, and to keep the logic true assume the block duration is 20 days and mezzaneins slab 5 days (no shutter to be removed because its( asteel sheeted suspended slab) ,the mezzaneine slab starts after steel erection with alag (20 days) and the steel erection starts after slab on grade with alag (5) days.
* The Second Question is:
in p3 you can link activities using the relation (Finish to Start with a minues Lag which equals to the relation start to start with same lag but positive ) my question is which relation is correct or the more correct in performing ascheduale to be submitted to a consultant (to match the american specification and to keep the logic ,float and longest path correct )?
thanks alot for all comments
Regards M.Foudeh
i have (2) questions regarding the logic and sequencing in p3:
i will give an example to explain question (#1):
* the activity "block work" for ground floor starts after Steel Erection (its a steel structure building) and continue after the finish of mezzanine slab to complete the balance block there,my question is: what is the best method to link these activity, and to keep the logic true assume the block duration is 20 days and mezzaneins slab 5 days (no shutter to be removed because its( asteel sheeted suspended slab) ,the mezzaneine slab starts after steel erection with alag (20 days) and the steel erection starts after slab on grade with alag (5) days.
* The Second Question is:
in p3 you can link activities using the relation (Finish to Start with a minues Lag which equals to the relation start to start with same lag but positive ) my question is which relation is correct or the more correct in performing ascheduale to be submitted to a consultant (to match the american specification and to keep the logic ,float and longest path correct )?
thanks alot for all comments
Regards M.Foudeh
11 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?