Urgent Scheduling help please

Safak VuralMember for 18 years 5 months
Created
6
1
0
Dear all,

There is a problem with the actual resources and the estimate to complete when I am making a schedule update on a recently reforcasted schedule. I think everything is in order but I canot find the problem. I am updatin 6 schedules right now but I have problem only on this one. I need a urgent help.

Autocost rules are:
-Link remaining durations and sch % : checked
-Subtract actual from EAC: checked
-When quantity change, use current unit prices .....
all checked!!
-Use update % complete against budget to estimate
all checked!!
-Link Budget and EAC for non-progressed act: checked.
-Calculate variance as BUDGET-EAC: Checked
-Apply these.... Cell: checked.

Let me give you an example:
IN PREVIOUS FILE: in one activity&resource:
BUDGETED QTY:44677
ACTUAL TO DATE: 38868.99
TO COMPLETE: 5808.01
AT COMPLETION: 44677
VARIANCE: 0
%: 87.1
UPDATED SCHEDULE:
BUDGETED QTY:44677
ACTUAL TO DATE: 38958.34
TO COMPLETE: 46677(??????!!!!)
AT COMPLETION: 83635.34
VARIANCE: -38958.34
%: 87.2

It is making To complete same as the budgeted quantity and this is happening every file that has an update. I corrected this by hand from resource screen bu it is going to give me same problem every week. If someone has a suggestion I would be glad.

Best regards to all of the planners,

Safak VURAL

6 replies

Oldest first
  1. 0
    Pinan T. ·
    other than it is corrupted, do you use store period performance?
  2. 0
    David Kelly ·
    Pinan T.

    You do not make clear if you are updating the progress by typing it in or updating it from another source. Are you importing progress from excel?
  3. 0
    Safak Vural ·
    Thank you for your interest. I am both using store period performance and I am importing progresses and actual dates.
    Waiting for your reply.

    Safak
  4. 0
    Safak Vural ·
    Thank you for your support,

    I checked the project there are no corruption. I found the problem. The problem is coming from importing and exporting. When I updated activities by hand there are no problems. I changed the import and export tables. (All folders etc.) Problem solved. I am using .DBF to importing. If anyone has a more technical explanation. (like format of the file or extension of the folder vs.) I will be glad to hear it.

    Best Regards,

    Safak
  5. 0
    Ife Olyke ·
    I use DBF to import data into P3.

    In my case, progress import DBF file contains;
    Activity Id, % Complete, Actual Start (AS), Actual Finish (AF)

    My experience is that; if the first line item for AS or AF in the table is blank, then for some reasons, it changes AS or AF column to text; and if you happen not to check before importing, then you’ll probably import progress data with no finish dates. To get round it, I sort the data by AF, then by AS.

    If you copy and paste onto an existing DBF file, then you will have to delete and re-create the name...
  6. 0
    Safak Vural ·
    Than you all,

    Best Regards,