Project Risk Analysis
In the Open Standard
Dattatreya PadharthiMember for 23 years 6 months
- Created
- 1
- 1
0
Schedule Risk analysis itself is a complicated subject full of probabilities & statistics.
A robust schedule is a mandatory prerequisite for such an analysis.
A schedule where durations are governed by quantities (productivity).
But when it comes to activity relationships, things become really complicated. We can end up with number of possibilities between two activities.
E.g Piping Prefab & erection & their relationship (SS/FF).
At the start of the Project/Proposal stage how should we take care of these uncertainities in relationships?
A robust schedule is a mandatory prerequisite for such an analysis.
A schedule where durations are governed by quantities (productivity).
But when it comes to activity relationships, things become really complicated. We can end up with number of possibilities between two activities.
E.g Piping Prefab & erection & their relationship (SS/FF).
At the start of the Project/Proposal stage how should we take care of these uncertainities in relationships?
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?