Project Group & Targets

John ImpraimMember for 25 years 3 months
Created
3
2
0
Hi Guys,

I have 2 stand alone projects (with targets) which have been made sub-projects to a new project group. Now, how do I display their Targets at the project group level ?

Any help out there ?

John

3 replies

Oldest first
  1. 0
    Steven Oliver ·
    You would have to prefix the activity id’s in your target plan with the same prefix you used to create your sub-projects.

    This can be done with a Global Change (Actid = xx&actid), though depending on how your activity id is made up you may need to use the ltrim or left/right text functions.


    HTH
  2. 0
    Philip Jonker ·
    Hi john,

    If you have the two target projects, combine them in the same way you did with the updated projects, in a multi project file, and add the same sub-project id’s, and use this group as your new target.
  3. 0
    Sukumaran Subaramaniyan ·
    Make a copy of new project group (eg.PG01) and rename it (eg.PG02). The subproject will be copied together. Set PG01 as a baseline (target) schedule and PG02 as current working file. Go to Tools > Project Utilities > Targets and set PG01 as a target file for PG02.

    Regards.