Resource leveling
In the Open Standard
Achim KempfMember for 21 years 10 months
- Created
- 3
- 1
0
During Precommissioning one team has to do loop checks in 20 commissioning systems, which are partly related to each other. The systems contain 1 up to 250 loops. The team is able to handle 40 loops a day. How can I manage P3 to calculate the early start of the loopchecking per systemn respec. the sequence of the systems to be checked?
Regards Achim
Regards Achim