Resource leveling

Achim KempfMember for 21 years 10 months
Created
3
1
0
During Precommissioning one team has to do loop checks in 20 commissioning systems, which are partly related to each other. The systems contain 1 up to 250 loops. The team is able to handle 40 loops a day. How can I manage P3 to calculate the early start of the loopchecking per systemn respec. the sequence of the systems to be checked?

Regards Achim

3 replies

Oldest first
  1. 0
    Jaco Stadler ·
    Hi Achim

    I WOuld Suggest you go to the Following Method.

    1) Open a P3 Schedule (in Hours)
    2) Create the 20 Systems as Activity
    3) Calcultate the activity Durations

    Example assume System has 80 loops and you said 40 loops a Day (Assume 8 working hours) This mean activty duration is 16 hrs

    Do the system Inter Logic

    Assign a Resource "Loops" BQ (Number of loops / Systems)

    Press level (Assign the resource Loops) Make Normal & Max lvl 5 (40 loops /8 Hours)
  2. 0
    Achim Kempf ·
    Thanks Jaco it worked. Regards from Munich Achim
  3. 0
    Philip Jonker ·
    Hi achim,

    Forgotten me

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?