Assigning resource curves

Eckart SchenckMember for 21 years 4 months
Created
2
1
0
Hi guys,

I’ve got to change the resource curve of a number of activities. Now using xls import P3 creates a new resource instead of updating the existing one.

Any ideas?

Thanks
Heinz

2 replies

Oldest first
  1. 0
    Jaco Stadler ·
    Why Export.

    In p3 Organise by Resource. Show Column BQ & Curve. and Do it in P3.
  2. 0
    Dattatreya Padharthi ·
    Absolutely, if you have just one resource & you decide to change the curve based on your gut feeling, experience etc, you can do so by showing " Resource curve" columns.

    If you have more than one resources , resource curve columns will be empty.
    & if you have to change curves based on type of resources, groupings , codes etc (in an intelligent way) it is advisable to do so thru Global Change. Better Go for Global Change.

    Dattatreya