Skip to content

Activity Suspension

Adnan AmjadMember for 21 years 5 months
Created
5
2
0
I want to show the suspension on activity due to rain more than once in a week but in P3 u can show suspension of an activity only once have anyone got the solution.

5 replies

Oldest first
  1. 0
    Paul Silver ·
    Adnan,

    Consider modifying your calendar to reflect the rain days.

    Regards
    Paul Silver
  2. 0
    Adnan Amjad ·
    Right, for rainy days Calander holidays are most effective but if suspension is for any other reson effecting only that perticular activity more than once then is there any other alternative available then defining a new separate calander for that perticular activity.
  3. 0
    Steven Oliver ·
    If you have a need to retain the information, I would suggest that the most effective method would be to add new activities to describe the delay. In this way demonstration of the effect is much clearer and easily understood.

    HTH
  4. 0
    David Burrows ·

    I have a project that has 3

    I have a project that has 3 periods of total suspension that needs to be built into the schedule.  

    Each period will be for a minimum of 14 days and while the suspendion of work is known ahead of time, the project period does not include the 42 days involved.  

    Is there a way to show the planned 14 day work suspensions without the time accruing against the total project time? 

     

    THANK YOU FOR YOUR ASSITANCE. 

     

    David R Burrows

  5. 0
    Mike Testro ·

    Hi DavidPut it on the

    Hi David

    Put it on the calendar as non work days.

    Best regards

    Mike T.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?