Copy acivities

Santosh PurohitMember for 21 years 8 months
Created
7
3
0
hi,
I have a program which had 24th floors and from 3rd onwards all floors are same.Now floors have been incraesed to 37 typical floors. which would be the best way to copy the activities to of a typical floor to other floors. i m using fragnets but want to know if there would be any other method which is fast as i m already havin 50000 activities in the whole program.
Also i have inserted some activities and putting relations is a problem as i cant fillcell so how to insert a relation similar in following ones

thanks

Santosh

7 replies

Oldest first
  1. 0
    Raja Izat Raja Ibrahim ·
    hi santosh,

    why dont u use import export???

    rizat
  2. 0
    Santosh Purohit ·
    Thanks for d reply

    how is that ?? plz help... do u want me to convert it to MPX??

    santosh
  3. 0
    Raja Izat Raja Ibrahim ·
    hi..
    actually i don t know what software u use..just generally gave the informtion...if p3 see as below..
    - make a back up first.have try with simple data first
    - u just go to tools
    - export,
    - select one topic...
    - setup the data u wanted to be copied...then after that
    - open the in spreadsheet file u can copied the activities in the spreadsheet
    -then save.
    - go to tools import bac the data where u save it
    -lastly have a look first...try to explore

    cheers...have a nice day

  4. 0
    Steven Oliver ·
    But, that would not maintain relationships.

    Either copy from within P3 (which would maintain relationships) or use fragnets.


    HTH


  5. 0
    Raja Izat Raja Ibrahim ·
    dear santosh,

    its depends on the creativity of the planner either way...
    in terms of quickiest way we can use fragnet, but in terms of awareness we can use import / export.

    c.c steven

    regards
  6. 0
    Steven Oliver ·
    Awareness of what ?
  7. 0
    Raja Izat Raja Ibrahim ·

    awareness of making mistake if the relation or the resources is not being full copied automaticly so we can double check on the spreadsheet itself thats my opinion another thing at least we got the data backup because i have an experience when we doing fragnet the pc is hang..so the data corrupt. thats what i mean. cheer up man.

Log in or join to reply