how copy bands and activity all togather in one step

Shahzad AhmadMember for 18 years 9 months
Created
6
39
0
Hi-

I am using P3.1

I want to make copy of bands and activites in one step

i am trying to copy band but it is not working only activities are copying.

Did any one expert in P3 who can guide me how to copy a Bands .

Thanks
shahzad

6 replies

Oldest first
  1. 0
    Gün Göksu ·
    Hi Shahzad,

    1. you can use fragnets. this will copy the relationships as well.

    2. you can export the relationships and reimport for the new actids.

    band? do you mean the title band?
    that gets created according to your organization settings.
    for that check the wbs or the act code data.

    hope the above will answer you question.
    Regards
    Gün Göksu
  2. 0
    Shahzad Ahmad ·
    Hello Gun

    Thanks for your prompt reply.

    i want copyt past some Bands(title Bands) under my wbs bands which i had allready created.

    how i can copy or ...

    Thanks
  3. 0
    Sajid Balma ·
    Hi Shehzad
    Have you been using P6 or P5. This can be done in P5 & p6 not in P3.
    To create same layout in P3, you have no option but to set a layout based on either your WBS or activity code.
  4. 0
    Shahzad Ahmad ·
    Hi-sajid.

    i got it ...it is not possible in p3
  5. 0
    Gün Göksu ·
    It is possible in P3.
    you can not copy/paste the bands.
    but you can export & import the wbs or actcodes and do a reorganize.
  6. 0
    Gün Göksu ·
    if the bands under the wbs are the same but located elsewhere then you need to change the wbs data of the peculiar actids for them to apply to the new band as you say it.

    you can use the fill row command too.

    further info is in the manuals.

    regards.
    Gün Göksu