Copying activity data description

Yves TrudelMember for 21 years 2 months
Created
10
4
0
Hello all,
I’m trying to copy activity data from one field to another. I succeed in copying the codes, but I dont know how to copy descriptions.
Any hint?
Thanks in advance
Yves

10 replies

Oldest first
  1. 0
    Yves Trudel ·
    Just a little precision: I work with global change. I created a new activity code and I want to copy what I had in the existing code.
    i.e. TXT1 EQ TXT0
    In this case I get the proper code, but not the description.
    I tried TXT1 EQ TTL(TXT0)
    But I get only the first characters of the title, and I dont get the field code.
    By the way, the goal is to move the activity code field to a different position.
    Still hoping for help
    ;-)
    Yves
  2. 0
    Sen Moc ·
    Yves,

    Move the Activity Code to a different position???

    Try Format/Columns. There you can add, delete, INSERT column headings to your preference locations.

    Regards,
    Sen
  3. 0
    Christian Adrian De Vera ·
    Hello Yves,

    You could also try to export it to excel and include also the data(s) you need then you can do the copy&paste faster... Just a thought..

    Cheers!

    Christian
  4. 0
    Jackie Gilliland ·
    Hi Yves

    If I understand correctly, you have created a new code which you would like to add to a group of activities.
    If this is the case this should work for you.

    -In the "Format/Column" tag, add a new column for this code field

    -Now select an activity coded to this field, or if you have none select one of the activities you would like to allocate the code to and add it manually.

    -Next ensure this code field column is visible on your screen and click your cursor on this code.

    -Then highlight all activities you would like to allocate this code to.

    I hate to shout but this is important.

    ENSURE YOUR CURSOR IS STILL ON THE CODE YOU WOULD LIKE TO COPY and that the activities you would like to allocate the code to are highlighted.

    -Now select "Edit/Fill Cell"

    This should solve your problem

    Good Luck
    Jackie Gilliland
  5. 0
    Se de Leon ·
    Hi Yves,

    I’m afraid you have to redo the activity code description. Code descriptions to my understanding can not be imported or exported only the code values. Unless someone out there has a better solution.

    Cheers,

    Se
  6. 0
    Ganesan Sebrenmani ·
    hi,

    i agree with jackie. it’s the easiest way to copy an items codes or description to another.

    insert the column, highlight and fill cells.

    cheers.
  7. 0
    Se de Leon ·
    Hi Ganesan,

    Are you sure you can copy activity "code description" using fill cell command? In fill cell command you can only copy activity "codes" or values not its description. Please note I highlighted the words code description and codes(values).

    Cheers,

    Se
  8. 0
    Hannes de Bruyne ·
    Hello Yves,

    I think you still have to be more precise. What do you want to copy? The code values (in Data, than use transfer) or the assigned code values (in general view, than use one of the proposed replies). In this case however global change also works if you use it in the right way.


    Regards

    Hannes
  9. 0
    Jackie Gilliland ·
    Hi Yves

    I will try again

    If it is only the activity code description titles you are attempting to copy, I am not sure that there is a quick way of doing this.

    The easiest I could think of is:

    Go to your "Data Code Directory", I understand you have created your code values.

    Go to the code title you would like to copy and highlight the title in your "Data Entry Box"

    Copy the description (mouse right click) and past this to the appropriate field against your new code.

    I trust this will solve your problem.

    Jackie Gilliland
  10. 0
    Yves Trudel ·
    Good morning to all!
    Yes, I undesstand I had to be more precise. What I am working at is to rearrange the activity codes in the "Activity Form" at screen bottom. The code TXT0 is in position 3 (Data / Activity codes /Activity codes)
    As I want to uniformize 4 different projects to merge into a Project Group, I deduct I need to sort their activity codes in the same rank.
    The activity code TXT0 exist only in one of the files and I presume it has to be moved away in order to get all projects forms compatible, or at least more convenient to use for any of the "sub projects" I want to create.
    I tought I had only to renumber the code rank in the "activity form" dialog box, but I could not. So I decide to create a new activity code at the bottom of the existing ones, and make a global change to populate it. This is where I need help: I get the proper codes, but I loose all descriptions. So if I delete the TXT0 code, I have to work with a separate document to keep explanation of the moved codes.

    In this case Jackie and Sigfredo have the proper understanding.
    Thank you all again, it is a great pleasure to see all that team spirit to help.

    Yves