deleting selected relationships
In the Open Standard
Gün GöksuMember for 21 years 6 months
- Created
- 2
- 1
0
Hello, :)
I have a big amount of activities that each have a certain amount of relationships.
basically I would like to delete a whole set of relationships.
How do I do it?
any way of exporting all of the successor relationships to dbf and creating a new column with DELETE and choseing which to delete? but I want to leave the rest of the relationships as is. (there is a lot of it).
for example export of P3SUC.DBF:
ACT SUC LAG REL
L0001.CS05 L0001.CS06 0 FS
L0001.CS05 L0001.CS16 0 FS
L0002.CS05 L0002.CS06 0 FS
L0002.CS05 L0002.CS16 0 FS
L0003.CS05 L0003.CS06 0 FS
L0003.CS05 L0003.CS16 0 FS
L0004.CS05 L0004.CS06 0 FS
L0004.CS05 L0004.CS16 0 FS
becoming:
ACT SUC LAG REL DELETE
L0001.CS05 L0001.CS06 0 FS D
L0001.CS05 L0001.CS16 0 FS
L0002.CS05 L0002.CS06 0 FS D
L0002.CS05 L0002.CS16 0 FS
L0003.CS05 L0003.CS06 0 FS D
L0003.CS05 L0003.CS16 0 FS
L0004.CS05 L0004.CS06 0 FS D
L0004.CS05 L0004.CS16 0 FS
import back and voila??
so basically I want to remove a set of relationships leaving the rest and the activities alone.
anyone can show me a way? c’ause I can add new relationships with import. but cant delete.
Thank you. :)
Gün. :)
I have a big amount of activities that each have a certain amount of relationships.
basically I would like to delete a whole set of relationships.
How do I do it?
any way of exporting all of the successor relationships to dbf and creating a new column with DELETE and choseing which to delete? but I want to leave the rest of the relationships as is. (there is a lot of it).
for example export of P3SUC.DBF:
ACT SUC LAG REL
L0001.CS05 L0001.CS06 0 FS
L0001.CS05 L0001.CS16 0 FS
L0002.CS05 L0002.CS06 0 FS
L0002.CS05 L0002.CS16 0 FS
L0003.CS05 L0003.CS06 0 FS
L0003.CS05 L0003.CS16 0 FS
L0004.CS05 L0004.CS06 0 FS
L0004.CS05 L0004.CS16 0 FS
becoming:
ACT SUC LAG REL DELETE
L0001.CS05 L0001.CS06 0 FS D
L0001.CS05 L0001.CS16 0 FS
L0002.CS05 L0002.CS06 0 FS D
L0002.CS05 L0002.CS16 0 FS
L0003.CS05 L0003.CS06 0 FS D
L0003.CS05 L0003.CS16 0 FS
L0004.CS05 L0004.CS06 0 FS D
L0004.CS05 L0004.CS16 0 FS
import back and voila??
so basically I want to remove a set of relationships leaving the rest and the activities alone.
anyone can show me a way? c’ause I can add new relationships with import. but cant delete.
Thank you. :)
Gün. :)
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?