Actual dates to change

Yves TrudelMember for 21 years 2 months
Created
4
1
0
Hi everyone,
Is there a simple way to change actual dates for a large number of activities ?
Thank you in advance for your help
Yves

4 replies

Oldest first
  1. 0
    Philip Jonker ·
    Hi there,
    Why would you be wanting to change the actual dates? It is simple to do but not acceptable. Either somebody has been lying or else.
  2. 0
    Yves Trudel ·
    Just because actual dates were put in by mistake. The activities were 100% but actual starts and ends should be changed to correspond with reality.
  3. 0
    Raja Izat Raja Ibrahim ·
    Hi Yves,
    U can use global change, or import/export...
    1.if u going to use global change u can look sample in p3 how they use it. It will run automaticly after u run the global change , be careful u have to backup the file first.
    in case the output is not like u wanted u can use your backup.

    Actually not advisable to use global change... it will effect your budget course, manhours etc. and it become dispute...I recomend u change manually, one by one...
    It quiet risky and tedious. I did this before, but once is enough, after that incident ... i have my backup each time, i want to update the progress.
    have a try...cheers
  4. 0
    Yves Trudel ·
    Thank you very much, I just saw it!

Log in or join to reply