"PROJ environment variable is too long"

David MosesMember for 21 years 11 months
Created
6
3
0
Hi Dear Pioneers;

Just now I received an error message "PROJ environment variable is too long" while I was trying to filter my project.I have almost 6500 activities.
What could be the reason? Is there any one who faced same problem before?

I also tried to export this file but I could not manage it because of this same error message...

Please help me.

6 replies

Oldest first
  1. 0
    Raja Izat Raja Ibrahim ·
    David,
    use PFXW.exe in p3win /p3 progs... or u have to recopy to another new file using impor export ...just guess...maybe this is because some of your layout or your setup is not apply to p3 programme... so the software become crazy. not joking... i have experiencing this problem before. One thing i know about this software ...its very sensitive and have to follow like sequencing.
    good luck.. have a try
  2. 0
    David Moses ·
    Raja Izat Raja Ibrahim

    I tried your solution.But It did not work. :(
  3. 0
    Raja Izat Raja Ibrahim ·

    if u trust me, u can send your file i try to fix for you, if not confidential..miharbiz@yahoo.com
  4. 0
    David Moses ·
    Hi Bill Guthrie,

    Thanks for your help....That is the solution I was looking for.

    That is why I like this PLANNING PLANET !!!

    Thanks to all.
  5. 0
    Raja Izat Raja Ibrahim ·
    Hi bill,
    may be sombody have to compile all the problem / solution for P3, we can call "Pocket manual book for P3" ....somtimes its the same problem but the problem is to recall back the memory to reconize the problem is difficult
  6. 0
    Steven Oliver ·
    If I remember correctly, the maximum length of the string pointing to the location of the P3 files is 64 characters.

    Wasnt so much of a problem, with 16-bit architecture where directory names where limited to 8 characters, but in 32/64 bit systems, people have got used to identifying directories with longer titles.