changing unit price does not affect on Budgeted Cost ??
In the Open Standard
Onur OzerMember for 21 years 1 month
- Created
- 6
- 2
0
Hi,
i changed the unit price value of a resource . Old one 100$ , new value is ZERO . Since total BQ is 10, total cost- according to me- must be low down 100x10= 1000 $ . But i see total COST TO COMPLETE keep its old value .
Can you say the reason?, when i change unit price why CTC doesn’t affect .
Thanks..
i changed the unit price value of a resource . Old one 100$ , new value is ZERO . Since total BQ is 10, total cost- according to me- must be low down 100x10= 1000 $ . But i see total COST TO COMPLETE keep its old value .
Can you say the reason?, when i change unit price why CTC doesn’t affect .
Thanks..