Dear All;

I uploaded my resources to the hammock activities to make things easy and simple at the beginning of the developing a Master Schedule.

How could I Level this Schedule?Since I Uploaded resources to the hammocks.

Any suggestions?

Thanks

1 reply

Oldest first
  1. 0
    Sukumaran Subaramaniyan ·
    David,

    IMO upload the resources to hammock is not a correct way to do the resource loaded schedule. When you assign the resources to hammock, the resouces will be distributed evenly from begining to ending of the activity.

    Whereby when you assign the resources to the detail activities, a specific activity contains a specific resources. By this way resources would not be jumbled up all in one and you can monitor the movement of the resources easily without much hassle. Also you know when you really need them to perform the work at site.

    Again, the best way to upload the resources to an activity is by assigning it to detail activities and not to a hammock.

    Regards.