EV uses budget from current or target project?
In the Open Standard
Vanessa MorrisMember for 21 years 3 months
- Created
- 2
- 1
0
Hi, in Tools->Options->Earned Value, P3 asks "when calculating earned and planned values, use the budget from?", and then gives two options: 1) Current project, 2) Target Project. By default, the current project is selected. Theory says that we use current projects and target projects in order to measure performance. So, if we are going to use current project and not the target, isn’t this a contradiction? shouldn’t the target project be selected by default? If the target project is not selected, then why do we create one? I’ll wait for the comments of the experts. Thank you.
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?