planned cost

Ayman EleishMember for 21 years
Created
1
1
0
Is there a way to compare by the late target cost on the main layout instead of early target cost(planned).
thanks

1 reply

Oldest first
  1. 0
    Raja Izat Raja Ibrahim ·
    U can insert column Schedule variance (BCWS-BCWP). or u can ceate another using global change, as u like. for reference "how to use global change" u can go to P3 sample or go to old post thread in PP.
    further question ...just reply.