Resource Percent Complete

Amar AghanaMember for 21 years 2 months
Created
2
2
0
Hi Guys,

I want to run a global change to show Resource Percent Complete (RCP) equal to Percent Complete(PCT)

1) How to create a global change command for this.

I tried RCP EQ PCT

RCP is not a correct command.

2) By entering Resource Percent Complete (RCP)also while updating, I hope we will be projecting resource requirement correctly for the balance period.

Please advise.

2 replies

Oldest first
  1. 0
    Yves Trudel ·
    Use RPCT equals PCT
    Yves Trudel
  2. 0
    Yves Trudel ·
    Yes I use Primavera 3.1
    What I am suggesting is really to put these expected finish dates only on activities that have an actual start, meaning that I have a strong reference to foresee their finish dates.
    It prevents me to be obliged to bring back their end dates after moving the data date. When you have large quantities of activities to update every week, I still believe that this could ease the planner job.
    I hope I will find some supporters!
    ;-)
    YVes