levelling of resources

Sunil KumarMember for 21 years
Created
4
1
0
once i do levelling of a particular resource... and scheduling it will again come to where i started... how can i retain the schedule as it is( i mean levelled schedule)

4 replies

Oldest first
  1. 0
    Hemanth Kumar ·
    Not Possible My Friend
    Levelling gives scenarios
    if you want to retain dates note it down and constrain activities
  2. 0
    Ronald Winter ·
    It is easy to remember scenarios. Create Custom Data Fields for the Early Dates and then use global edit to transfer the leveled dates into this new field. Done! Good luck.
  3. 0
    Zhang Haixiang ·
    Sunil,

    I agree with Ronald. Creat a custon data item to store leveled date for reference.

    and be careful using constraints. After updating your schedule, you’d better re-schedule and re-leveling, because critical path/total float/free float may change, the result of leveling will also change.
  4. 0
    Alex Wong ·
    Echo.......................

    Back to the original question

    What I normally do is to save a copy of the levelled schedule as a target schedule for later reference.

    In addition, the reason that you don’t really need to keep the schedule becasue each time the senario changes you will need to re-level your schedule base on the new conditions. What you however need to save is your levelling setup.
    Priority, Float control...

    HTH

    Alex

Log in or join to reply