Conversion from Primavera P3 to MS Project 2003

Norzul IbrahimMember for 20 years 10 months
Created
1
1
0
Is it possible? How?

Thanks

norzul

1 reply

Oldest first
  1. 0
    Manulal Inasu ·
    1.Choose tools,MPX conversion utility
    2.click P3 icon
    3.select the project.
    4.click OK
    5.give a name for the converted file.
    6.Click OK

    Regards,

    Manu.